Bank Communication Hub

One shared view for you, Kaiāulu Credit Union, and Haleakalā Builders.

Released to date

$184,500

Held by the bank

$182,400

Next draw

Draw 4

Draw schedule

  1. Draw 1 — Site prep & debris

    $42,000

    Released Mar 14 · inspection passed

  2. Draw 2 — Foundation

    $68,000

    Released May 2 · inspection passed

  3. Draw 3 — Framing

    $74,500

    Released last week · funds wired to builder

  4. Draw 4 — Rough-in (mechanical, electrical, plumbing)

    $61,200

    Awaiting contractor sign-off on the lien waiver packet

  5. Draw 5 — Drywall & finishes

    $58,000

    Unlocks after the Draw 4 inspection clears

What's blocking the next release

Sign and return the Draw 4 lien waiver packet

Owner: Your contractor

Owed since Monday

Upload the updated builder's risk insurance certificate

Owner: You

Needed before release

Schedule the third-party progress inspection

Owner: Kaiāulu Credit Union

Queued — 3-5 business days